Overview
Wear parts are the largest variable cost on a Tracked Jaw Crusher Plant. HAMAC supplies matched consumables and a recommended stock list with every plant.

Main consumables
- Chamber liners / blow bars / Impact plates.
- Rotors, distributor plates and anvils (VSI).
- Screen meshes for every deck.
- Belts, bearings, seals and sensors.
Liner material grade
Mn13 / Mn18 / Mn22 work-harden under impact; high-chrome resists abrasion in low-impact duties. Choice follows the rock, not the price.
Recommended stock
- One full set of chamber liners or blow bars.
- Screen meshes for every deck.
- Belts, bearings and seals.
- Electrical consumables and sensors.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Tracked Jaw Crusher Plant |
| Category | Tracked Crushing Plants |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | single-project view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and single-project operating plan.
Published Tracked Jaw Crusher Plant model data
| Model | MJ150SE | MJ260E | MJ-350E | MJ-450SE |
|---|---|---|---|---|
| Feeder | ||||
| Volume(m³) | 4 | 6 | 6 | 6 |
| Feeding height(mm) | 3500 | 4357 | 4357 | 4357 |
| Maximum feed size(mm) | 430 | 560 | 630 | 720 |
| Crusher | ||||
| Host model | MC80 | MC106 | MC113 | MC120 |
| Feed opening(mm) | 800×510 | 1060X700 | 1130×750 | 1200×870 |
| Closed side setting(mm) | 40-175 | 70-200 | 70-200 | 70-200 |
Take productivity to the next level with the HMC Series Tracked Jaw Crusher Plant. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | minimal civil works |
| Evaluation horizon | single-project view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for tracked jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
For a mixed local and expatriate team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Local service partner, technician travel time and visa requirements for your market.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Product sampling points and the lab equipment needed for routine grading checks.
- Dust and noise control designed to the local emission limits for your market.
- After-sales response time, technician availability and the warranty exclusions in writing.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On demolition and recycling duties, the minimal civil works objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying minimal civil works on price alone and losing it in availability.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
Review the list with a mixed local and expatriate team before the order is placed — they will recognise most of them.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Dry-run the plant empty for the specified period and record vibration.
- Confirm the direction and tension of every belt under no load.
The commissioning record becomes the reference for every liner change in the single-project plan.