Design basis for manganese ore underground mine
The design basis starts with the rock, not the machine. Manganese ore is rated at 60–180 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.85 t/m³. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. A change in one stage changes the circulating load in all the others.
A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of sized lump and fines for smelting.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Manganese ore · 60–180 MPa · abrasion medium |
| Design throughput | 100 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | sized lump and fines for smelting |
| Loose bulk density | 1.85 t/m³ |
| Suggested circuit | jaw → impact → screen → washing |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a manganese ore underground mine this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For manganese ore at 100 t/h the working train is jaw → impact → screen → washing. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for manganese ore and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.85 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 300 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 20% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, sized lump and fines for smelting |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 300 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for manganese ore, while compact footprint determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
