● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Environment

Manganese ore high-altitude site: Noise and vibration — solution & design basis

Noise limits at the site boundary are exceeded — a 110 t/h design basis, configuration and acceptance checks.

Manganese ore high-altitude site with noise and vibration is normally resolved by checking the circuit against the saleable product specification first: isolate screen and crusher mounts and maintain them. For a 110 t/h design point on manganese ore, HAMAC would review jaw → impact → screen → washing, then confirm the settings with a written acceptance test. Written acceptance criteria prevent a dispute turning into a redesign.

110 t/hindicative design point
60–180 MPacompressive strength
100–250 t/hscenario capacity band
270 kWorder-of-magnitude installed power
Key takeaways
  1. Manganese ore is medium in abrasiveness and medium in moisture sensitivity; Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages.
  2. For high-altitude site the priority is drive and cooling margins, constrained by reduced air density and large day/night temperature swings.
  3. Noise and vibration typically appears as: noise limits at the site boundary are exceeded.
  4. First corrective action: isolate screen and crusher mounts and maintain them.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for manganese ore high-altitude site

The design basis starts with the rock, not the machine. Manganese ore is rated at 60–180 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.85 t/m³. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. Indicative values are starting points for a design, not guarantees.

A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 650 mm and target fractions of sized lump and fines for smelting.

Manganese ore — design basis (nominal values)
ParameterIndicative value / method
Raw materialManganese ore · 60–180 MPa · abrasion medium
Design throughput110 t/h saleable product (100–250 t/h scenario band)
Maximum feed size~650 mm
Target productsized lump and fines for smelting
Loose bulk density1.85 t/m³
Suggested circuitjaw → impact → screen → washing
Manganese ore high-altitude site — Design basis for manganese ore high-altitude site — HAMAC crushing and screening equipment
Manganese ore high-altitude site — Design basis for manganese ore high-altitude site — HAMAC crushing and screening equipment reference.

Why noise and vibration appears in this circuit

Noise limits at the site boundary are exceeded. In a manganese ore high-altitude site this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.

  • the crusher and screen are mounted without adequate isolation
  • the plant is arranged with its loudest face toward the boundary
  • worn bearings and loose liners add impact noise

Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) measure boundary noise at the worst-case operating state; 2) log vibration on screen bearings; 3) inspect isolation mounts during planned stops. Ask for the mass balance and the test method behind any quoted number.

Recommended equipment configuration

For manganese ore at 110 t/h the working train is jaw → impact → screen → washing. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for manganese ore and for a softer rock. Indicative values are starting points for a design, not guarantees.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~138 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~30 mm at the secondary stage
Secondary / tertiaryimpact
ScreeningMulti-deck screen sized for 30% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.85 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 270 kW order-of-magnitude connected load

The corrective actions for noise and vibration are applied on top of this base circuit: isolate screen and crusher mounts and maintain them; orient the plant and use stockpiles as acoustic barriers; replace worn bearings and re-torque liner fasteners.

Manganese ore high-altitude site — Recommended equipment configuration — HAMAC crushing and screening equipment
Manganese ore high-altitude site — Recommended equipment configuration — HAMAC crushing and screening equipment reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 30% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.

  • Measure boundary noise at the worst-case operating state
  • Log vibration on screen bearings
  • Inspect isolation mounts during planned stops
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 110 t/h nominal
GradingFull sieve analysis, agreed standard, sized lump and fines for smelting
Crusher settingCSS measured and logged, ~30 mm starting point
PowerMain-drive current at steady feed, 270 kW connected load
WearLiner mass before and after, cost per saleable tonne

Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for manganese ore, while drive and cooling margins determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.

  • Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Indicative values are starting points for a design, not guarantees. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Manganese ore high-altitude site — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment
Manganese ore high-altitude site — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment reference.
FAQ

Manganese ore high-altitude site — questions answered

Direct answers to the questions buyers ask most often.

What causes noise and vibration in a manganese ore high-altitude site?

Noise limits at the site boundary are exceeded. The usual causes are the crusher and screen are mounted without adequate isolation; the plant is arranged with its loudest face toward the boundary; worn bearings and loose liners add impact noise. isolate screen and crusher mounts and maintain them.

Which crusher train suits manganese ore at 100–250 t/h?

A typical configuration is jaw → impact → screen → washing. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 110 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call