Design basis for andesite high-altitude site
The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. Record the setting before adjusting it, or the baseline is lost.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Andesite · 120–240 MPa · abrasion medium–high |
| Design throughput | 110 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | asphalt aggregate, 0–5, 5–16 mm |
| Loose bulk density | 1.44 t/m³ |
| Suggested circuit | jaw → cone → VSI → screen |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a andesite high-altitude site this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For andesite at 110 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.44 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 320 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 30% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 320 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while drive and cooling margins determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
