● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Commissioning

Andesite quarry expansion: Tramp metal damage — solution & design basis

A bucket tooth or rebar reaches the chamber and damages liners — a 150 t/h design basis, configuration and acceptance checks.

Andesite quarry expansion with tramp metal damage is normally resolved by checking the circuit against the saleable product specification first: fit a magnetic separator and a belt metal detector. For a 150 t/h design point on andesite, HAMAC would review jaw → cone → VSI → screen, then confirm the settings with a written acceptance test. Most of these problems are diagnosed at the screen, not at the crusher.

150 t/hindicative design point
120–240 MPacompressive strength
150–300 t/hscenario capacity band
440 kWorder-of-magnitude installed power
Key takeaways
  1. Andesite is medium–high in abrasiveness and low in moisture sensitivity; Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification.
  2. For quarry expansion the priority is throughput continuity, constrained by a shared feed point and limited stockpile area.
  3. Tramp metal damage typically appears as: a bucket tooth or rebar reaches the chamber and damages liners.
  4. First corrective action: fit a magnetic separator and a belt metal detector.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for andesite quarry expansion

The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. Record the setting before adjusting it, or the baseline is lost.

A quarry expansion must add saleable output without stopping the existing line, constrained by a shared feed point and limited stockpile area. The commercial priority is throughput continuity. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.

Andesite — design basis (nominal values)
ParameterIndicative value / method
Raw materialAndesite · 120–240 MPa · abrasion medium–high
Design throughput150 t/h saleable product (150–300 t/h scenario band)
Maximum feed size~300 mm
Target productasphalt aggregate, 0–5, 5–16 mm
Loose bulk density1.44 t/m³
Suggested circuitjaw → cone → VSI → screen
Andesite quarry expansion — Design basis for andesite quarry expansion — HAMAC impact crusher
Andesite quarry expansion — Design basis for andesite quarry expansion — HAMAC impact crusher reference.

Why tramp metal damage appears in this circuit

A bucket tooth or rebar reaches the chamber and damages liners. In a andesite quarry expansion this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.

  • no magnet or detector ahead of the crusher
  • hydraulic relief and tramp-release settings are untested
  • demolition feed is not pre-sorted

Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Agree the acceptance test and sampling method before the order is placed.

Recommended equipment configuration

For andesite at 150 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. Record the setting before adjusting it, or the baseline is lost.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~188 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~34 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 20% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.44 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 440 kW order-of-magnitude connected load

The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Andesite quarry expansion — Recommended equipment configuration — HAMAC impact crusher
Andesite quarry expansion — Recommended equipment configuration — HAMAC impact crusher reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 20% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.

  • Test the detector with a sample metal piece each week
  • Inspect the chamber after any release event
  • Log every tramp incident and its cause
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 150 t/h nominal
GradingFull sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm
Crusher settingCSS measured and logged, ~34 mm starting point
PowerMain-drive current at steady feed, 440 kW connected load
WearLiner mass before and after, cost per saleable tonne

Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while throughput continuity determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.

  • Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Record the setting before adjusting it, or the baseline is lost. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Andesite quarry expansion — Cost, risk and what to confirm in writing — HAMAC impact crusher
Andesite quarry expansion — Cost, risk and what to confirm in writing — HAMAC impact crusher reference.
FAQ

Andesite quarry expansion — questions answered

Direct answers to the questions buyers ask most often.

What causes tramp metal damage in a andesite quarry expansion?

A bucket tooth or rebar reaches the chamber and damages liners. The usual causes are no magnet or detector ahead of the crusher; hydraulic relief and tramp-release settings are untested; demolition feed is not pre-sorted. fit a magnetic separator and a belt metal detector.

Which crusher train suits andesite at 150–300 t/h?

A typical configuration is jaw → cone → VSI → screen. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 150 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call