Design basis for manganese ore high-altitude site
The design basis starts with the rock, not the machine. Manganese ore is rated at 60–180 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.85 t/m³. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. Operator notes from the first month are often the best diagnostic data.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of sized lump and fines for smelting.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Manganese ore · 60–180 MPa · abrasion medium |
| Design throughput | 100 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | sized lump and fines for smelting |
| Loose bulk density | 1.85 t/m³ |
| Suggested circuit | jaw → impact → screen → washing |

Why excessive liner consumption appears in this circuit
Liner sets are replaced far more often than the budget assumed. In a manganese ore high-altitude site this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- the alloy does not match feed abrasiveness
- the crusher is running with a worn chamber profile
- tramp metal is reaching the chamber
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) weigh each liner set before and after use; 2) calculate cost per saleable tonne; 3) photograph the chamber at every change-out. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For manganese ore at 100 t/h the working train is jaw → impact → screen → washing. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for manganese ore and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.85 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 270 kW order-of-magnitude connected load |
The corrective actions for excessive liner consumption are applied on top of this base circuit: select manganese grade against measured silica content; rotate or replace liners before the profile is lost; install a magnet and metal detector on the feed belt.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 20% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Weigh each liner set before and after use
- Calculate cost per saleable tonne
- Photograph the chamber at every change-out
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, sized lump and fines for smelting |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 270 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for manganese ore, while drive and cooling margins determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.