Overview
A practical River pebble crushing plant configuration by capacity, with the equipment list and screening setup that HAMAC typically specifies.

30–100 t/h
- Primary jaw (PE series).
- Secondary impact or small cone.
- 2-deck screen for 2–3 products.
- Wheel or tracked for mobility.
100–300 t/h
- Primary jaw + secondary cone.
- 3-deck screen, multiple fractions.
- Dust control and conveyors.
- Stationary or modular.
300–800 t/h
- Large jaw or gyratory primary.
- Two-stage cone train.
- Multiple screens and stockpiles.
- PLC control, full dust suppression.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | River pebble |
| Mohs hardness | 7 |
| Compressive strength | ~120 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone + VSI |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | single-project view |
At contract crushing on short-term sites, the ranking of these parameters changes: minimal civil works usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | minimal civil works |
| Evaluation horizon | single-project view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for river pebble crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Review the crusher chamber profile with the liner supplier against River pebble (Mohs 7, ~120 MPa, high abrasion).
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
Shortening this sequence is possible on a brownfield extension, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for your market.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Closed-side setting range and whether automatic setting regulation is included.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Decommissioning or relocation value at the end of a single-project horizon.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Guaranteed power draw and the minimal civil works trade-off it implies.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
A single-project view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Using one liner profile for both secondary and tertiary stages.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
The commissioning record becomes the reference for every liner change in the single-project plan.