Overview
Selecting a crusher for dolomite is about matching the breakage mechanism to the rock: compression for hard abrasive stone, impact for soft stone that needs shape.

Primary stage
- Jaw crusher: handles the largest feed, robust on hard rock.
- For Dolomite: a jaw or even a hammer/impact primary for soft stone.
Secondary / tertiary
- Impact crusher: high reduction and cubical shape at lower cost.
- Add VSI only when sand or strict shape is required.
Common mistakes
- Undersizing the primary (causes bridging).
- Using impact crushers on very high-abrasion rock (blow-bar blow-out).
- Ignoring screen area (bottlenecks the whole line).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Dolomite |
| Mohs hardness | 3.5 |
| Compressive strength | ~110 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on dolomite crushing; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | strict product cubicity |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for dolomite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Survey the feed: Dolomite (Mohs 3.5, ~110 MPa, low abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Apply jaw + impact; the reduction mechanism must suit low abrasion and a compressive strength near 110 MPa.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Dust and noise control designed to the local emission limits for your market.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Closed-side setting range and whether automatic setting regulation is included.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
Share this list with an owner-operator team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Buying strict product cubicity on price alone and losing it in availability.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Using one liner profile for both secondary and tertiary stages.
For seasonal road-project supply, protect the strict product cubicity requirement explicitly in the contract documents.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Sample each product fraction and compare with the specification.
- Record the baseline grading curve for each product fraction.
- Calibrate the belt scale and any level probes against a known load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify rotation direction on every motor before coupling.
- Test emergency stops, pull wires and interlock trips in sequence.
On a brownfield extension, allow extra time for the dust and noise measurements.