Overview
A river pebble crushing plant turns raw river pebble into graded aggregate, ore feed or industrial mineral. Material properties — Mohs 7, compressive strength ~120 MPa, high abrasion — decide the circuit.

River pebble material profile
| Property | Value |
|---|---|
| Mohs hardness | 7 |
| Compressive strength | 120 MPa |
| Abrasion | High |
| Recommended circuit | jaw + cone + VSI |
Recommended circuit
HAMAC configures River pebble plants as: jaw + cone + VSI. High silica; VSI essential for manufactured sand.
Typical equipment
- PE Series Jaw Crusher — Jaw crushers are often used for primary crushing in mine material crushing.
- HPT Multi-Cylinder Hydraulic Cone Crusher — Hydraulic multi-cylinder cone crusher for secondary and tertiary crushing of limestone thr
- VSI Vertical Shaft Impact Crusher (Sand Making Machine) — VSI sand making machine, 60–500 t/h, for manufactured sand and aggregate shaping with rock
Capacity range
From 30 t/h contractor units to 1,000+ t/h quarry lines, with multi-deck screening for several saleable fractions.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | River pebble |
| Mohs hardness | 7 |
| Compressive strength | ~120 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone + VSI |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for river pebble crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Survey the feed: River pebble (Mohs 7, ~120 MPa, high abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Apply jaw + cone + VSI; the reduction mechanism must suit high abrasion and a compressive strength near 120 MPa.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Closed-side setting range and whether automatic setting regulation is included.
- Product sampling points and the lab equipment needed for routine grading checks.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Liner alloy: Mn13 is a common starting point for river pebble at high abrasion.
- After-sales response time, technician availability and the warranty exclusions in writing.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a high-abrasion feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
For mine pre-beneficiation feed, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm the direction and tension of every belt under no load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Sample each product fraction and compare with the specification.
- Verify rotation direction on every motor before coupling.
The commissioning record becomes the reference for every liner change in the five-year plan.