Overview
River pebble crushing plant cost scales with capacity, mobility and wear-package grade. The table below gives an indicative bracket by plant size.

Indicative cost by capacity
| Plant size | Indicative scope | Cost driver |
|---|---|---|
| < 100 t/h | mobile jaw + screen | mobility & simplicity |
| 100–300 t/h | jaw + cone + screens | model size & liners |
| > 500 t/h | multi-stage stationary | throughput & automation |
What moves the price
- Capacity and number of crushing stages.
- Mobility (stationary < wheel < tracked).
- Wear-part grade and spare-parts package.
- Screen area, conveyors and dust control.
Get a budget
Send material, feed size, target t/h and products for a configured FOB / CIF budget within 24 hours.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | River pebble |
| Mohs hardness | 7 |
| Compressive strength | ~120 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone + VSI |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for river pebble crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Apply jaw + cone + VSI; the reduction mechanism must suit high abrasion and a compressive strength near 120 MPa.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Control system language, telemetry and remote diagnostics availability.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Local service partner, technician travel time and visa requirements for your market.
- Liner alloy: Mn18 with ceramic inserts is a common starting point for river pebble at high abrasion.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On mine pre-beneficiation feed, the lowest cost per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Using one liner profile for both secondary and tertiary stages.
- Comparing quotations with different port terms and calling the lower number cheaper.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Test emergency stops, pull wires and interlock trips in sequence.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Dry-run the plant empty for the specified period and record vibration.
- Calibrate the belt scale and any level probes against a known load.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
On a brownfield extension, allow extra time for the dust and noise measurements.