Overview
Choosing a Vibrating Screen starts with the rock and the target product, not a catalogue number. The steps below turn your project data into a defensible model choice.

1. Start with the material
- Hard, abrasive rock (granite, basalt, quartz): compression crushing, premium Mn liners.
- Soft rock (limestone, marble, dolomite): impact crushing for shape at lower cost.
- High silica (river pebble, quartz): plan VSI + wear budget.
2. Size to saleable t/h
Add 10–20% surge to nameplate capacity; undersizing is a permanent bottleneck, oversizing wastes capital.
3. Match the product grading
Product size and shape (flakiness index) decide chamber and screen deck setup.
Pre-order checklist
- Feed size and max lump.
- Required t/h and product fractions.
- Site power (voltage / frequency) and mobility need.
- Local standards (CE, GOST, etc.).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Vibrating Screen |
| Category | Supporting Equipments |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
Ask for the same table from any competing supplier; without it, an offer for vibrating screen cannot be compared on scope.
Published Vibrating Screen model data
| Model | Mesh Qty | Mesh Size | Freq | Capacity | Power | Dimension |
|---|---|---|---|---|---|---|
| YK1236 | 1 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 5.5 kW | 4110×1757×970 |
| 2YK1236 | 2 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 7.5 kW | 4142×1748×1340 |
| 3YK1236 | 3 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 11 kW | 4215×1748×1488 |
| 4YK1236 | 4 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 15 kW | 4336×1748×1840 |
| YK1545 | 1 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 11 kW | 4970×2048×823 |
| 2YK1545 | 2 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 15 kW | 5573×2110×1582 |
| 3YK1545 | 3 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 15 kW | 5610×2110×1776 |
| 4YK1545 | 4 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 18.5 kW | 5798×2110×2191 |
The YK Series Circular Vibrating Screen is designed for screening various ores and building materials, suitable for materials with moisture content no more than 5%. Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | three-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for vibrating screen may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.

From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.
What to verify before you sign
- Written performance guarantee, sampling method and acceptance-test protocol.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Product sampling points and the lab equipment needed for routine grading checks.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Decommissioning or relocation value at the end of a three-year horizon.
- Local service partner, technician travel time and visa requirements for your market.
- Wear-part interchangeability across machines in the same circuit.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Assuming the manufacturer's warranty covers wear parts and consumables.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Record power draw, tonnage and chamber pressure at steady state.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check lubrication levels, grease lines and oil cooler operation.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Confirm the direction and tension of every belt under no load.
- Sample each product fraction and compare with the specification.
- Check belt tracking, chute build-up and transfer-point dust.
The commissioning record becomes the reference for every liner change in the three-year plan.