Overview
The Belt Conveyor is applied across aggregates, mining, beneficiation and recycling. The material properties decide whether it is the right machine.

Materials it handles
- Hard rock: granite, basalt, andesite, gabbro.
- Soft rock: limestone, marble, dolomite.
- Ores: iron, copper, gold, manganese.
- Recycling: concrete, asphalt, C&D waste.
Industries
- Quarrying and construction aggregates.
- Metal ore crushing and beneficiation.
- Manufactured sand and road base.
- Cement raw meal and industrial minerals.
Typical configuration
Usually combined with a feeder, screen and conveyors into a complete circuit, or as a module in a mobile plant.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Belt Conveyor |
| Category | Supporting Equipments |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Belt Conveyor model data
| Section Form | Belt speed (m/s) | Widtd of belt |
|---|---|---|
| 500 | 650 | 800 |
| U type | 0.8 | 78 |
| 1 | 97 | 169 |
| 1.25 | 122 | 206 |
| 1.6 | 156 | 264 |
| 2 | 191 | 323 |
| 2.5 | 232 | 391 |
| 3.15 |
HAMAC offers high-performance Mining Equipment Conveyor Belt Systems, ideal for transporting aggregate, sand, and other bulk materials. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | three-year view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for belt conveyor may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Local service partner, technician travel time and visa requirements for your market.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Control system language, telemetry and remote diagnostics availability.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
For contract crushing on short-term sites, give the maximum mechanical availability line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Using one liner profile for both secondary and tertiary stages.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Assuming the manufacturer's warranty covers wear parts and consumables.
Review the list with a mixed local and expatriate team before the order is placed — they will recognise most of them.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Calibrate the belt scale and any level probes against a known load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
Keep the signed record; it is the only defensible baseline for later performance disputes.