Overview
The minimum gap between the mantle and concave (or jaw plates) at the discharge end of the crushing chamber, measured at the tightest point of the cycle.

Why it matters in practice
- Sets the top size of the product
- Smaller CSS raises fines, power draw and liner wear
- Measured with a lead plug or an electronic setting system
- Recheck after every liner change
Applying it to plant selection
Engineers use closed side setting (css) together with feed gradation, moisture content and target tonnage when fixing the flow sheet. HAMAC records the value in the project data sheet so the equipment list, liner grade and motor rating can be checked against the written performance guarantee.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | single-project view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | single-project view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Book shipping, prepare the packing list and confirm the container loading plan.
For a small contractor crew, the commissioning and training steps need more calendar time than the mechanical erection itself.
What to verify before you sign
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Guaranteed power draw and the lowest cost per tonne trade-off it implies.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Local service partner, technician travel time and visa requirements for your market.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Closed-side setting range and whether automatic setting regulation is included.
- Dust and noise control designed to the local emission limits for your market.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On mine pre-beneficiation feed, the lowest cost per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Using one liner profile for both secondary and tertiary stages.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping a geotechnical check and discovering settlement under the primary crusher at an existing quarry bench.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Overlooking dust, noise and water permits in your market until erection has already started.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Record the baseline grading curve for each product fraction.
- Dry-run the plant empty for the specified period and record vibration.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
The commissioning record becomes the reference for every liner change in the single-project plan.