Overview
A 50–100 tph crushing plant is one of the most requested export sizes. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Cost factors
- Number of crushing stages.
- Mobility (stationary < wheel < tracked).
- Wear-parts grade and automation.
- Screen area, conveyors, dust control.
50–100 TPH budget drivers
| Scope | Impact on price |
|---|---|
| Mobility | tracked adds hydraulic & engine cost |
| Stages | more stages = more machines |
| Automation | PLC + remote monitoring increases cost |
| Spares | recommended stock adds upfront value |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Assumed duty | continuous quarry production |
| Evaluation horizon | five-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and five-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for 50–100 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.
What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Decommissioning or relocation value at the end of a five-year horizon.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 50–100 t/h.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Local service partner, technician travel time and visa requirements for your market.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in your market until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Sample each product fraction and compare with the specification.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record power draw, tonnage and chamber pressure at steady state.
For a rotating shift crew, run through this list twice — once with the supervisor and once without.