Overview
Bauxite (Mohs 2, ~50 MPa, low abrasion): processing steps, equipment and cost notes for plant buyers.

Processing steps
- Primary crushing — jaw.
- Secondary / tertiary — jaw + impact.
- Screening for graded products.
- Dewatering / handling.
Recommended equipment
- PE Series Jaw Crusher
- PF Impact Crusher
- Vibrating Screen
Cost notes
Operating cost is dominated by wear parts on low-abrasion material; choose liner grade by rock, not price.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Bauxite |
| Mohs hardness | 2 |
| Compressive strength | ~50 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
Ask for the same table from any competing supplier; without it, an offer for bauxite crushing cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | fast mobilisation |
| Evaluation horizon | seven-year view |
| Site condition | a coastal export terminal |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for bauxite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Review the crusher chamber profile with the liner supplier against Bauxite (Mohs 2, ~50 MPa, low abrasion).
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
On contract crushing on short-term sites, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Local service partner, technician travel time and visa requirements for your market.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Choke-feed arrangement: surge bin, feeder control and level indication.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 55% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For bauxite crushing at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Using one liner profile for both secondary and tertiary stages.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Assuming the manufacturer's warranty covers wear parts and consumables.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify rotation direction on every motor before coupling.
The commissioning record becomes the reference for every liner change in the seven-year plan.