Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Morocco, from quotation to commissioning.

Shipping & port
- Destination: Casablanca.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 380V 50Hz.
- Standards: NM.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Morocco customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Casablanca |
| Site supply | 380V 50Hz |
| Local standards | NM |
| Region | Africa |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | seven-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Morocco.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Product sampling points and the lab equipment needed for routine grading checks.
- Wear-part interchangeability across machines in the same circuit.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Nameplate data for 380V 50Hz and the NM certificate set.
For manufactured-sand production, give the lowest energy per tonne line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A seven-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Calibrate the belt scale and any level probes against a known load.
- Verify rotation direction on every motor before coupling.
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
The commissioning record becomes the reference for every liner change in the seven-year plan.