Overview
Practical, numbers-first guidance on the Vibrating Screen — written for engineers specifying, buying and running crushing plants.

Capacity factors
- Chamber / CSS and material.
- Feed gradation and moisture.
- Screen efficiency downstream.
- Continuous vs surge feed.
Rule of thumb
Rated capacity is stated at a given CSS and material; treat it as saleable product, not crusher throughput. Size the plant to 10–20% above target.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Vibrating Screen |
| Category | Supporting Equipments |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on vibrating screen; they are nominal and should be confirmed against a sample test before manufacture.
Published Vibrating Screen model data
| Model | Mesh Qty | Mesh Size | Freq | Capacity | Power | Dimension |
|---|---|---|---|---|---|---|
| YK1236 | 1 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 5.5 kW | 4110×1757×970 |
| 2YK1236 | 2 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 7.5 kW | 4142×1748×1340 |
| 3YK1236 | 3 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 11 kW | 4215×1748×1488 |
| 4YK1236 | 4 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 15 kW | 4336×1748×1840 |
| YK1545 | 1 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 11 kW | 4970×2048×823 |
| 2YK1545 | 2 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 15 kW | 5573×2110×1582 |
| 3YK1545 | 3 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 15 kW | 5610×2110×1776 |
| 4YK1545 | 4 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 18.5 kW | 5798×2110×2191 |
The YK Series Circular Vibrating Screen is designed for screening various ores and building materials, suitable for materials with moisture content no more than 5%. Read the table column by column against high-tonnage aggregate supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for vibrating screen may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Book shipping, prepare the packing list and confirm the container loading plan.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Dust and noise control designed to the local emission limits for your market.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Product sampling points and the lab equipment needed for routine grading checks.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Control system language, telemetry and remote diagnostics availability.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Using one liner profile for both secondary and tertiary stages.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a coastal export terminal.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Confirm the direction and tension of every belt under no load.
- Verify rotation direction on every motor before coupling.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check belt tracking, chute build-up and transfer-point dust.
- Measure noise and dust at the operator position against the local limit.
- Calibrate the belt scale and any level probes against a known load.
The commissioning record becomes the reference for every liner change in the ten-year plan.