Overview
Practical, numbers-first guidance on the KJ Series Modular Crushing & Screening Plant — written for engineers specifying, buying and running crushing plants.

Capacity factors
- Chamber / CSS and material.
- Feed gradation and moisture.
- Screen efficiency downstream.
- Continuous vs surge feed.
Rule of thumb
Rated capacity is stated at a given CSS and material; treat it as saleable product, not crusher throughput. Size the plant to 10–20% above target.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | KJ Series Modular Crushing & Screening Plant |
| Category | Modular Crushing Plant |
| Assumed duty | continuous quarry production |
| Evaluation horizon | ten-year view |
Ask for the same table from any competing supplier; without it, an offer for kj series modular crushing & screening plant cannot be compared on scope.
Published KJ Series Modular Crushing & Screening Plant model data
| Plant type | Model | Standard device | Vehicle-mounted device | Capacity (t/h) | Transport dimensions (mm) |
|---|---|---|---|---|---|
| Jaw crusher plant | KJ98 | GZDT9538 | HDX98 | 90–350 | 12750 × 3020 × 3850 |
| Jaw crusher plant | KJ110 | GZDT1145B | HDX110 | 120–450 | 13050 × 3050 × 4000 |
| Impact crusher plant | KJ1213 | GZDT9538 | C11213 | 80–320 | 12970 × 3020 × 3920 |
| Impact crusher plant | KJ1316 | GZDT1145B | C11316 | 100–400 | 13290 × 3050 × 4080 |
| Cone crusher plant | K1300 | — | HPM300C1 | 60–280 | 15650 × 3270 × 3780 |
| Cone crusher plant | KJ250 | — | SC250F1 | 90–350 | 15600 × 3270 × 3800 |
| Sand maker plant | KJ0926 | — | HVI0926 | 85–240 | 15400 × 2770 × 3780 |
| Sand maker plant | KJ1040 | — | HVI1040 | 120–284 | 15400 × 2920 × 3970 |
KJ modular stations for jaw, impact, cone, VSI sand making and screening, 60–500 t/h, with foundation-free installation and transportable dimensions. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for kj series modular crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Local service partner, technician travel time and visa requirements for your market.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Closed-side setting range and whether automatic setting regulation is included.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Dust and noise control designed to the local emission limits for your market.
- Product sampling points and the lab equipment needed for routine grading checks.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the ten-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For kj series modular crushing & screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Buying maximum mechanical availability on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Comparing quotations with different port terms and calling the lower number cheaper.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record power draw, tonnage and chamber pressure at steady state.
- Calibrate the belt scale and any level probes against a known load.
- Dry-run the plant empty for the specified period and record vibration.
Keep the signed record; it is the only defensible baseline for later performance disputes.