Overview
Dolomite (Mohs 3.5, ~110 MPa, low abrasion): processing steps, equipment and cost notes for plant buyers.

Processing steps
- Primary crushing — jaw.
- Secondary / tertiary — jaw + impact.
- Screening for graded products.
- Dewatering / handling.
Recommended equipment
- PE Series Jaw Crusher
- PF Impact Crusher
Cost notes
Operating cost is dominated by wear parts on low-abrasion material; choose liner grade by rock, not price.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Dolomite |
| Mohs hardness | 3.5 |
| Compressive strength | ~110 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | seven-year view |
Treat this as a living sheet. Every revision of the flow sheet for your market should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a greenfield site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for dolomite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Control system language, telemetry and remote diagnostics availability.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Wear-part interchangeability across machines in the same circuit.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 16% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a low-abrasion feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record power draw, tonnage and chamber pressure at steady state.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
The commissioning record becomes the reference for every liner change in the seven-year plan.