Overview
Practical, numbers-first guidance on the Compound Cone Crusher — written for engineers specifying, buying and running crushing plants.

Preparation
- Confirm foundation per HAMAC layout.
- Check power and cable routing.
- Lift and level on grout.
Commissioning
- Dry run, then graded load.
- Set CSS and verify product.
- Train operators.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Compound Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
These values are the starting point for a written proposal on compound cone crusher; they are nominal and should be confirmed against a sample test before manufacture.
Published Compound Cone Crusher model data
| Model | Cavity Type | Stroke | Feed Limit | Exit Aperture | Capacity | Motor Power | Weight |
|---|---|---|---|---|---|---|---|
| HMC1650C2-D | Coarse | 34 mm | 300 mm | 35-65 mm | 280-610 t/h | 250 kw | 35 t |
| HMC1650C-D | Coarse | 34 mm | 260 mm | 30-60 mm | 265-580 t/h | 250 kw | 35 t |
| HMC1650Z-D | Medium Coarse | 34 mm | 240 mm | 25-60 mm | 240-550 t/h | 250 kw | 35 t |
| HMC1650S-X | Fine | 28 mm | 130 mm | 20-45 mm | 180-350 t/h | 250 kw | 35 t |
| HMC1400C-D | Coarse | 30 mm | 235 mm | 30-60 mm | 210-530 t/h | 220 kw | 25 t |
| HMC1400Z-D | Medium Coarse | 30 mm | 215 mm | 25-50 mm | 200-500 t/h | 220 kw | 25 t |
| HMC1400Z-X | Medium Coarse | 25 mm | 180 mm | 22-45 mm | 180-475 t/h | 220 kw | 25 t |
| HMC1400S-X | Fine | 25 mm | 100 mm | 19-40 mm | 130-260 t/h | 220 kw | 25 t |
HMC series compound spring cone crusher is a more convenient cone crusher which is researched on the base of traditional spring cone crusher. Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for an existing quarry bench in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for compound cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
A HAMAC project manager stays with the order from the first data sheet through hand-over in your market.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Written performance guarantee, sampling method and acceptance-test protocol.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Local service partner, technician travel time and visa requirements for your market.
Ask each supplier to price the same list. Quotations for compound cone crusher only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Calibrate the belt scale and any level probes against a known load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Record the baseline grading curve for each product fraction.
On an existing quarry bench, allow extra time for the dust and noise measurements.