Overview
Practical, numbers-first guidance on the Vibrating Screen — written for engineers specifying, buying and running crushing plants.

Abnormal noise / vibration
- Check for loose liner bolts or foreign metal in feed.
- Verify foundation bolts and coupling alignment.
- Listen for bearing distress; schedule replacement.
Low output
- Worn liners / blow bars reduce reduction.
- Wrong CSS / setting for target product.
- Screen blinding limits throughput.
Poor product shape
- Increase reduction in the shaping stage.
- Verify VSI rotor speed / anvil.
- Re-check screen mesh.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Vibrating Screen |
| Category | Supporting Equipments |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | seven-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Published Vibrating Screen model data
| Model | Mesh Qty | Mesh Size | Freq | Capacity | Power | Dimension |
|---|---|---|---|---|---|---|
| YK1236 | 1 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 5.5 kW | 4110×1757×970 |
| 2YK1236 | 2 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 7.5 kW | 4142×1748×1340 |
| 3YK1236 | 3 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 11 kW | 4215×1748×1488 |
| 4YK1236 | 4 | 4.32 ㎡ | 800-900 r/min | 25-200 m³/h | 15 kW | 4336×1748×1840 |
| YK1545 | 1 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 11 kW | 4970×2048×823 |
| 2YK1545 | 2 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 15 kW | 5573×2110×1582 |
| 3YK1545 | 3 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 15 kW | 5610×2110×1776 |
| 4YK1545 | 4 | 6.75 ㎡ | 800-900 r/min | 45-380 m³/h | 18.5 kW | 5798×2110×2191 |
The YK Series Circular Vibrating Screen is designed for screening various ores and building materials, suitable for materials with moisture content no more than 5%. Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for vibrating screen may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
Shortening this sequence is possible on a brownfield extension, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Product sampling points and the lab equipment needed for routine grading checks.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Control system language, telemetry and remote diagnostics availability.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For vibrating screen at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check belt tracking, chute build-up and transfer-point dust.
- Record the baseline grading curve for each product fraction.
- Confirm all guards, emergency stops and pull-wire switches function.
- Dry-run the plant empty for the specified period and record vibration.
On a brownfield extension, allow extra time for the dust and noise measurements.