Overview
A turnkey contract covers the flow sheet, manufacture, shipment to Algiers, civil reference drawings, erection supervision, commissioning and operator training — one project manager from enquiry to hand-over.

Scope of supply
- Site survey and material testing.
- Flow sheet, layout and foundation reference.
- Manufacture, workshop assembly and load test.
- Freight and customs documentation for Algeria.
- Erection supervision, 380V 50Hz power tie-in and training.
Market parameters for Algeria
| Item | Reference |
|---|---|
| Region | Africa |
| Port | Algiers |
| Voltage / frequency | 380V 50Hz |
| Standards | NA |
| Typical feed | Limestone, Aggregates |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Algiers |
| Site supply | 380V 50Hz |
| Local standards | NA |
| Region | Africa |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | seven-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | strict product cubicity |
| Evaluation horizon | seven-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Specify motors, starters and documentation for 380V 50Hz and NA before manufacture.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Algeria.
What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Product sampling points and the lab equipment needed for routine grading checks.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Local service partner, technician travel time and visa requirements for Algeria.
- Whether the quoted t/h is achieved at demolition and recycling duties or under ideal laboratory feed.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Algeria is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Overlooking dust, noise and water permits in Algeria until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record the baseline grading curve for each product fraction.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
On an existing quarry bench, allow extra time for the dust and noise measurements.