Overview
A 50–100 tph crushing plant is one of the most requested export sizes. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Why mobile at this size
- Fast relocation between benches / sites.
- Plug-and-produce, low civil work.
- Diesel-electric or grid power options.
Mobile types
- Wheel-mounted: lower cost, needs a tow.
- Tracked: self-propelled, rough terrain.
- 3-in-1 / 4-in-1: combined crush + screen.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Assumed duty | continuous quarry production |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | fast mobilisation |
| Evaluation horizon | ten-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Size the primary stage for 50–100 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Lay out the PE jaw + PF impact / cone + 2-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.
What to verify before you sign
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Product sampling points and the lab equipment needed for routine grading checks.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Wear-part interchangeability across machines in the same circuit.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Written performance guarantee, sampling method and acceptance-test protocol.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the ten-year review.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 50–100 t/h.
- Buying fast mobilisation on price alone and losing it in availability.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
On a confined urban yard, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Dry-run the plant empty for the specified period and record vibration.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Test emergency stops, pull wires and interlock trips in sequence.
For a small contractor crew, run through this list twice — once with the supervisor and once without.