Overview
Practical, numbers-first guidance on the Tracked Cone Crusher Plant — written for engineers specifying, buying and running crushing plants.

Capacity factors
- Chamber / CSS and material.
- Feed gradation and moisture.
- Screen efficiency downstream.
- Continuous vs surge feed.
Rule of thumb
Rated capacity is stated at a given CSS and material; treat it as saleable product, not crusher throughput. Size the plant to 10–20% above target.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Tracked Cone Crusher Plant |
| Category | Tracked Crushing Plants |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for tracked cone crusher plant cannot be compared on scope.
Published Tracked Cone Crusher Plant model data
| Model | MC200HRSE | MC300HRE | MC300HRSE | MC400HRSE |
|---|---|---|---|---|
| Feeder | ||||
| Volume(m³) | 6.5 | 6.5 | 6.5 | 6.5 |
| Feeding height(mm) | 2900 | 2870 | 2900 | 2560 |
| Maximum feed size(mm) | 185 | 225 | 225 | 275 |
| Feeding capacity(t/h) | 400 | 500 | 500 | 700 |
| Crusher | ||||
| Host model | HPC200 | HPC300 | HPC300 | HPC400 |
| Return screen length×width(mm) | 1740x5000 | 1740x5000 | 1740x5000 | 1800x5000 |
Maximize your productivity with the versatile Tracked Cone Crusher Plant! Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | fast mobilisation |
| Evaluation horizon | five-year view |
| Site condition | a coastal export terminal |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for tracked cone crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Confirm the haul-road and stockpile plan with a coastal export terminal in mind before fixing conveyor lengths.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Local service partner, technician travel time and visa requirements for your market.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the five-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Using one liner profile for both secondary and tertiary stages.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Comparing quotations with different port terms and calling the lower number cheaper.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Calibrate the belt scale and any level probes against a known load.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
- Measure and log the as-new CSS / setting for future wear comparison.
On a coastal export terminal, allow extra time for the dust and noise measurements.