Overview
A 200–300 tph crushing plant is one of the most requested export sizes. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Site requirements
- Level pad ~800–1,500 m².
- Power: standard grid at local voltage.
- Water for dust control (if fitted).
- Stockpile and truck-loading space.
Civil work
Foundations are referenced from the HAMAC general layout; a geotechnical check is recommended for > 300 t/h plants.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | three-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | three-year view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.
What to verify before you sign
- Wear-part interchangeability across machines in the same circuit.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Closed-side setting range and whether automatic setting regulation is included.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Decommissioning or relocation value at the end of a three-year horizon.
- After-sales response time, technician availability and the warranty exclusions in writing.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 6% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at 200–300 t/h, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 200–300 t/h.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Review the list with a mixed local and expatriate team before the order is placed — they will recognise most of them.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Verify rotation direction on every motor before coupling.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm the direction and tension of every belt under no load.
- Calibrate the belt scale and any level probes against a known load.
On a remote mine site, allow extra time for the dust and noise measurements.