Overview
HAMAC equipment matched to industrial minerals & powder:

Equipment
- PE Series Jaw Crusher
- MTW European Type Grinding Mill
- PF Impact Crusher
- Vibrating Feeder
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Application | Industrial Minerals & Powder |
| Typical feed | Calcite, Barite, Gypsum, Dolomite |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | single-project view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | single-project view |
| Site condition | a brownfield extension |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
A HAMAC project manager stays with the order from the first data sheet through hand-over in your market.
What to verify before you sign
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Product sampling points and the lab equipment needed for routine grading checks.
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Closed-side setting range and whether automatic setting regulation is included.
- Dust and noise control designed to the local emission limits for your market.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the single-project review.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Buying lowest energy per tonne on price alone and losing it in availability.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
Review the list with a full-time plant team before the order is placed — they will recognise most of them.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Record power draw, tonnage and chamber pressure at steady state.
- Measure noise and dust at the operator position against the local limit.
- Check lubrication levels, grease lines and oil cooler operation.
On a brownfield extension, allow extra time for the dust and noise measurements.