Overview
Selected HAMAC references relevant to aggregates & quarry:

References
- 100-120tph mobile crushing and screening plant in Algeria
- 100-120tph mobile crushing and screening plant in Chile
- 1500t/d Gold Ore Processing Plant in Tanzania
- 150-180tph stationary crushing and screening plant in Jamaica
- 150tph stationary crushing and screening plant in Iraq
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Application | Aggregates & Quarry |
| Typical feed | Granite, Limestone, Basalt |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | seven-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.
What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Closed-side setting range and whether automatic setting regulation is included.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
Share this list with a mixed local and expatriate team as well as procurement; operators are the ones who live with the omissions.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On mine pre-beneficiation feed, the simple operator maintenance objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Buying simple operator maintenance on price alone and losing it in availability.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
For mine pre-beneficiation feed, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Sample each product fraction and compare with the specification.
- Verify rotation direction on every motor before coupling.
- Calibrate the belt scale and any level probes against a known load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
The commissioning record becomes the reference for every liner change in the seven-year plan.