Design basis for manganese ore greenfield plant
The design basis starts with the rock, not the machine. Manganese ore is rated at 60–180 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.85 t/m³. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. Indicative values are starting points for a design, not guarantees.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 220 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of sized lump and fines for smelting.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Manganese ore · 60–180 MPa · abrasion medium |
| Design throughput | 220 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | sized lump and fines for smelting |
| Loose bulk density | 1.85 t/m³ |
| Suggested circuit | jaw → impact → screen → washing |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a manganese ore greenfield plant this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For manganese ore at 220 t/h the working train is jaw → impact → screen → washing. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for manganese ore and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~275 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~34 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.85 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 700 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 40% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 220 t/h nominal |
| Grading | Full sieve analysis, agreed standard, sized lump and fines for smelting |
| Crusher setting | CSS measured and logged, ~34 mm starting point |
| Power | Main-drive current at steady feed, 700 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for manganese ore, while a verifiable mass balance determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 220 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.