Design basis for quartzite high-altitude site
The design basis starts with the rock, not the machine. Quartzite is rated at 150–300 MPa compressive strength with very high abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. The reference conditions should be attached to every figure quoted.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of high-specification aggregate and industrial sand.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Quartzite · 150–300 MPa · abrasion very high |
| Design throughput | 110 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | high-specification aggregate and industrial sand |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → screen |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a quartzite high-altitude site this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For quartzite at 110 t/h the working train is jaw → cone → cone → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for quartzite and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 30% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, high-specification aggregate and industrial sand |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 350 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for quartzite, while drive and cooling margins determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.