● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Commissioning

Quartzite high-altitude site: Start-up instability — solution & design basis

The plant cannot hold a steady feed during its first weeks — a 110 t/h design basis, configuration and acceptance checks.

Quartzite high-altitude site with start-up instability is normally resolved by checking the circuit against the saleable product specification first: ramp feed in defined steps and record power at each step. For a 110 t/h design point on quartzite, HAMAC would review jaw → cone → cone → screen, then confirm the settings with a written acceptance test. The cheapest fix is usually a settings change; the most expensive is a new machine.

110 t/hindicative design point
150–300 MPacompressive strength
100–250 t/hscenario capacity band
350 kWorder-of-magnitude installed power
Key takeaways
  1. Quartzite is very high in abrasiveness and low in moisture sensitivity; Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows.
  2. For high-altitude site the priority is drive and cooling margins, constrained by reduced air density and large day/night temperature swings.
  3. Start-up instability typically appears as: the plant cannot hold a steady feed during its first weeks.
  4. First corrective action: ramp feed in defined steps and record power at each step.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for quartzite high-altitude site

The design basis starts with the rock, not the machine. Quartzite is rated at 150–300 MPa compressive strength with very high abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. The reference conditions should be attached to every figure quoted.

A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of high-specification aggregate and industrial sand.

Quartzite — design basis (nominal values)
ParameterIndicative value / method
Raw materialQuartzite · 150–300 MPa · abrasion very high
Design throughput110 t/h saleable product (100–250 t/h scenario band)
Maximum feed size~350 mm
Target producthigh-specification aggregate and industrial sand
Loose bulk density1.52 t/m³
Suggested circuitjaw → cone → cone → screen
Quartzite high-altitude site — Design basis for quartzite high-altitude site — HAMAC mobile crushing plant
Quartzite high-altitude site — Design basis for quartzite high-altitude site — HAMAC mobile crushing plant reference.

Why start-up instability appears in this circuit

The plant cannot hold a steady feed during its first weeks. In a quartzite high-altitude site this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.

  • interlocks and feeder ramp rates were never tuned together
  • settings were changed without a commissioning log
  • operators were trained on a different circuit

Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. A signed settings log at handover protects both parties later.

Recommended equipment configuration

For quartzite at 110 t/h the working train is jaw → cone → cone → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for quartzite and for a softer rock. The reference conditions should be attached to every figure quoted.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~138 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~42 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 30% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.52 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load

The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Quartzite high-altitude site — Recommended equipment configuration — HAMAC mobile crushing plant
Quartzite high-altitude site — Recommended equipment configuration — HAMAC mobile crushing plant reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 30% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.

  • Verify every interlock in no-load and loaded runs
  • Sign off the settings log with both parties
  • Repeat a full sieve analysis after the first 100 hours
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 110 t/h nominal
GradingFull sieve analysis, agreed standard, high-specification aggregate and industrial sand
Crusher settingCSS measured and logged, ~42 mm starting point
PowerMain-drive current at steady feed, 350 kW connected load
WearLiner mass before and after, cost per saleable tonne

A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for quartzite, while drive and cooling margins determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.

  • Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

The reference conditions should be attached to every figure quoted. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

FAQ

Quartzite high-altitude site — questions answered

Direct answers to the questions buyers ask most often.

What causes start-up instability in a quartzite high-altitude site?

The plant cannot hold a steady feed during its first weeks. The usual causes are interlocks and feeder ramp rates were never tuned together; settings were changed without a commissioning log; operators were trained on a different circuit. ramp feed in defined steps and record power at each step.

Which crusher train suits quartzite at 100–250 t/h?

A typical configuration is jaw → cone → cone → screen. Extreme silica content makes liner consumption the dominant operating cost; impact stages are avoided wherever the specification allows. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 110 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call