Design basis for manganese ore greenfield plant
The design basis starts with the rock, not the machine. Manganese ore is rated at 60–180 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.85 t/m³. Fines losses are the main economic issue, so washing and careful screen selection usually follow the crushing stages. Measurements are only comparable when the sieve standard is the same.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 210 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of sized lump and fines for smelting.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Manganese ore · 60–180 MPa · abrasion medium |
| Design throughput | 210 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | sized lump and fines for smelting |
| Loose bulk density | 1.85 t/m³ |
| Suggested circuit | jaw → impact → screen → washing |

Why long relocation and set-up time appears in this circuit
The plant loses more days to moving and erection than the contract allows. In a manganese ore greenfield plant this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- electrical and conveyor connections differ between modules
- transport permits and axle loads were checked too late
- no written set-up sequence exists for the crew
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For manganese ore at 210 t/h the working train is jaw → impact → screen → washing. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for manganese ore and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~263 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.85 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 460 kW order-of-magnitude connected load |
The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 30% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Time a full move from stop to first feed
- Count lifting operations and crane hours
- Record every connection that needs a tool on site
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 210 t/h nominal |
| Grading | Full sieve analysis, agreed standard, sized lump and fines for smelting |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 460 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for manganese ore, while a verifiable mass balance determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 210 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.