Design basis for basalt high-altitude site
The design basis starts with the rock, not the machine. Basalt is rated at 150–300 MPa compressive strength with high abrasiveness, low moisture sensitivity and a loose bulk density around 1.50 t/m³. Very abrasive and tough; wear cost per tonne, not peak throughput, usually decides the circuit and the liner alloy. Operator notes from the first month are often the best diagnostic data.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 130 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of railway ballast, 0–5, 5–16, 16–31.5 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Basalt · 150–300 MPa · abrasion high |
| Design throughput | 130 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | railway ballast, 0–5, 5–16, 16–31.5 mm |
| Loose bulk density | 1.50 t/m³ |
| Suggested circuit | jaw → cone → VSI → 3-deck screen |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a basalt high-altitude site this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For basalt at 130 t/h the working train is jaw → cone → VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for basalt and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~163 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.50 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 290 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 50% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 130 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast, 0–5, 5–16, 16–31.5 mm |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 290 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for basalt, while drive and cooling margins determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 130 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.