Design basis for gold ore remote site
The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. Record the setting before adjusting it, or the baseline is lost.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gold ore · 60–200 MPa · abrasion medium |
| Design throughput | 100 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | −10 mm mill feed or heap-leach agglomerate |
| Loose bulk density | 1.80 t/m³ |
| Suggested circuit | jaw → cone / impact → screen |

Why frequent site relocation appears in this circuit
A stationary plant cannot follow the working face economically. In a gold ore remote site this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.
- haul distance grows as the face advances
- civil foundations make relocation a major project
- the contract duration is shorter than the plant payback period
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) verify transport width and axle loads for local roads; 3) confirm set-up can be done with the site crane available. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For gold ore at 100 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | cone / impact |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.80 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 320 kW order-of-magnitude connected load |
The corrective actions for frequent site relocation are applied on top of this base circuit: use wheel or tracked units with on-board screens; design modular skids that fit standard container dimensions; standardise electrical plug-in connections between modules.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 60% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Time a full move from stop to first feed
- Verify transport width and axle loads for local roads
- Confirm set-up can be done with the site crane available
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 320 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while energy and spares autonomy determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.