● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Mobile plants

Gold ore remote site: Frequent site relocation — solution & design basis

A stationary plant cannot follow the working face economically — a 100 t/h design basis, configuration and acceptance checks.

Gold ore remote site with frequent site relocation is normally resolved by checking the circuit against the saleable product specification first: use wheel or tracked units with on-board screens. For a 100 t/h design point on gold ore, HAMAC would review jaw → cone / impact → screen, then confirm the settings with a written acceptance test. The answer depends on the mass balance, not on a catalogue capacity figure.

100 t/hindicative design point
60–200 MPacompressive strength
60–180 t/hscenario capacity band
320 kWorder-of-magnitude installed power
Key takeaways
  1. Gold ore is medium in abrasiveness and medium in moisture sensitivity; Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage.
  2. For remote site the priority is energy and spares autonomy, constrained by diesel generation and infrequent service visits.
  3. Frequent site relocation typically appears as: a stationary plant cannot follow the working face economically.
  4. First corrective action: use wheel or tracked units with on-board screens.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for gold ore remote site

The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. Record the setting before adjusting it, or the baseline is lost.

A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.

Gold ore — design basis (nominal values)
ParameterIndicative value / method
Raw materialGold ore · 60–200 MPa · abrasion medium
Design throughput100 t/h saleable product (60–180 t/h scenario band)
Maximum feed size~300 mm
Target product−10 mm mill feed or heap-leach agglomerate
Loose bulk density1.80 t/m³
Suggested circuitjaw → cone / impact → screen
Gold ore remote site — Design basis for gold ore remote site — HAMAC mobile crushing plant
Gold ore remote site — Design basis for gold ore remote site — HAMAC mobile crushing plant reference.

Why frequent site relocation appears in this circuit

A stationary plant cannot follow the working face economically. In a gold ore remote site this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.

  • haul distance grows as the face advances
  • civil foundations make relocation a major project
  • the contract duration is shorter than the plant payback period

Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) verify transport width and axle loads for local roads; 3) confirm set-up can be done with the site crane available. A signed settings log at handover protects both parties later.

Recommended equipment configuration

For gold ore at 100 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. Record the setting before adjusting it, or the baseline is lost.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~125 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~38 mm at the secondary stage
Secondary / tertiarycone / impact
ScreeningMulti-deck screen sized for 60% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.80 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 320 kW order-of-magnitude connected load

The corrective actions for frequent site relocation are applied on top of this base circuit: use wheel or tracked units with on-board screens; design modular skids that fit standard container dimensions; standardise electrical plug-in connections between modules.

Gold ore remote site — Recommended equipment configuration — HAMAC mobile crushing plant
Gold ore remote site — Recommended equipment configuration — HAMAC mobile crushing plant reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 60% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.

  • Time a full move from stop to first feed
  • Verify transport width and axle loads for local roads
  • Confirm set-up can be done with the site crane available
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 100 t/h nominal
GradingFull sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate
Crusher settingCSS measured and logged, ~38 mm starting point
PowerMain-drive current at steady feed, 320 kW connected load
WearLiner mass before and after, cost per saleable tonne

A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while energy and spares autonomy determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.

  • Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Record the setting before adjusting it, or the baseline is lost. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Gold ore remote site — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant
Gold ore remote site — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant reference.
FAQ

Gold ore remote site — questions answered

Direct answers to the questions buyers ask most often.

What causes frequent site relocation in a gold ore remote site?

A stationary plant cannot follow the working face economically. The usual causes are haul distance grows as the face advances; civil foundations make relocation a major project; the contract duration is shorter than the plant payback period. use wheel or tracked units with on-board screens.

Which crusher train suits gold ore at 60–180 t/h?

A typical configuration is jaw → cone / impact → screen. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 100 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call