Design basis for granite railway ballast production
The design basis starts with the rock, not the machine. Granite is rated at 100–250 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.45 t/m³. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. Operator notes from the first month are often the best diagnostic data.
A railway ballast production must maximise the 25–50 mm fraction with minimal waste, constrained by strict flakiness and abrasion specifications. The commercial priority is yield of the saleable fraction. For this combination HAMAC works from an indicative design point of 170 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of 0–5, 5–10, 10–20, 20–40 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Granite · 100–250 MPa · abrasion medium–high |
| Design throughput | 170 t/h saleable product (150–350 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | 0–5, 5–10, 10–20, 20–40 mm |
| Loose bulk density | 1.45 t/m³ |
| Suggested circuit | jaw → cone → cone / VSI → 3-deck screen |

Why CAPEX justification appears in this circuit
The investment case compares purchase prices instead of lifetime cost. In a granite railway ballast production this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- quotes assume different flow sheets and mass balances
- freight, civils, erection and spares are excluded
- availability is assumed at 100% in the payback model
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For granite at 170 t/h the working train is jaw → cone → cone / VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for granite and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~213 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.45 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 460 kW order-of-magnitude connected load |
The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 40% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Request a mass balance with each quotation
- Confirm the Incoterm and named port
- Sensitivity-test the payback at 75% utilisation
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 170 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–10, 10–20, 20–40 mm |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 460 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for granite, while yield of the saleable fraction determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 170 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.