Design basis for copper ore port or terminal handling
The design basis starts with the rock, not the machine. Copper ore is rated at 80–220 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.90 t/m³. Product top size is set by the downstream mill, so a closed crushing circuit with tight screen control protects grinding energy. Indicative values are starting points for a design, not guarantees.
A port or terminal handling must load and unload at a predictable rate, constrained by surge capacity and ship / rail scheduling. The commercial priority is buffer and availability. For this combination HAMAC works from an indicative design point of 280 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of −12 mm mill feed.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Copper ore · 80–220 MPa · abrasion medium |
| Design throughput | 280 t/h saleable product (250–500 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | −12 mm mill feed |
| Loose bulk density | 1.90 t/m³ |
| Suggested circuit | jaw → cone → screen → grinding circuit |

Why CAPEX justification appears in this circuit
The investment case compares purchase prices instead of lifetime cost. In a copper ore port or terminal handling this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- quotes assume different flow sheets and mass balances
- freight, civils, erection and spares are excluded
- availability is assumed at 100% in the payback model
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For copper ore at 280 t/h the working train is jaw → cone → screen → grinding circuit. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for copper ore and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~350 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~34 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.90 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 830 kW order-of-magnitude connected load |
The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 34 mm, a circulating load around 50% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Request a mass balance with each quotation
- Confirm the Incoterm and named port
- Sensitivity-test the payback at 75% utilisation
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 280 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −12 mm mill feed |
| Crusher setting | CSS measured and logged, ~34 mm starting point |
| Power | Main-drive current at steady feed, 830 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for copper ore, while buffer and availability determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 280 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.