Design basis for granite remote site
The design basis starts with the rock, not the machine. Granite is rated at 100–250 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.45 t/m³. High compressive strength makes compression crushing the economic choice; an impact or VSI stage is added only when cubicity is specified. Operator notes from the first month are often the best diagnostic data.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 650 mm and target fractions of 0–5, 5–10, 10–20, 20–40 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Granite · 100–250 MPa · abrasion medium–high |
| Design throughput | 110 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~650 mm |
| Target product | 0–5, 5–10, 10–20, 20–40 mm |
| Loose bulk density | 1.45 t/m³ |
| Suggested circuit | jaw → cone → cone / VSI → 3-deck screen |

Why frequent site relocation appears in this circuit
A stationary plant cannot follow the working face economically. In a granite remote site this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- haul distance grows as the face advances
- civil foundations make relocation a major project
- the contract duration is shorter than the plant payback period
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) verify transport width and axle loads for local roads; 3) confirm set-up can be done with the site crane available. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For granite at 110 t/h the working train is jaw → cone → cone / VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for granite and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.45 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 270 kW order-of-magnitude connected load |
The corrective actions for frequent site relocation are applied on top of this base circuit: use wheel or tracked units with on-board screens; design modular skids that fit standard container dimensions; standardise electrical plug-in connections between modules.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 70% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Time a full move from stop to first feed
- Verify transport width and axle loads for local roads
- Confirm set-up can be done with the site crane available
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–10, 10–20, 20–40 mm |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 270 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for granite, while energy and spares autonomy determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.