Design basis for dolomite wet tropical climate
The design basis starts with the rock, not the machine. Dolomite is rated at 60–180 MPa compressive strength with low–medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.42 t/m³. Suits impact crushing and downstream grinding; the fines fraction is often the most valuable product. Operator notes from the first month are often the best diagnostic data.
A wet tropical climate must keep screening reliable through a long rainy season, constrained by high feed moisture and clay-bearing overburden. The commercial priority is wet screening and washing. For this combination HAMAC works from an indicative design point of 160 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of aggregate, agricultural lime, filler powder.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Dolomite · 60–180 MPa · abrasion low–medium |
| Design throughput | 160 t/h saleable product (120–300 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | aggregate, agricultural lime, filler powder |
| Loose bulk density | 1.42 t/m³ |
| Suggested circuit | impact crusher → screen → optional Raymond mill |

Why CAPEX justification appears in this circuit
The investment case compares purchase prices instead of lifetime cost. In a dolomite wet tropical climate this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- quotes assume different flow sheets and mass balances
- freight, civils, erection and spares are excluded
- availability is assumed at 100% in the payback model
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For dolomite at 160 t/h the working train is impact crusher → screen → optional Raymond mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for dolomite and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~200 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.42 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 430 kW order-of-magnitude connected load |
The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 60% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Request a mass balance with each quotation
- Confirm the Incoterm and named port
- Sensitivity-test the payback at 75% utilisation
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 160 t/h nominal |
| Grading | Full sieve analysis, agreed standard, aggregate, agricultural lime, filler powder |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 430 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for dolomite, while wet screening and washing determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 160 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.