Design basis for barite greenfield plant
The design basis starts with the rock, not the machine. Barite is rated at 30–100 MPa compressive strength with low abrasiveness, low moisture sensitivity and a loose bulk density around 2.20 t/m³. High density affects conveying and classification; the target is a narrow particle-size distribution, not maximum tonnage. Operator notes from the first month are often the best diagnostic data.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 230 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of 200–325 mesh weighting agent.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Barite · 30–100 MPa · abrasion low |
| Design throughput | 230 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | 200–325 mesh weighting agent |
| Loose bulk density | 2.20 t/m³ |
| Suggested circuit | jaw → impact → grinding mill → classifier |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a barite greenfield plant this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For barite at 230 t/h the working train is jaw → impact → grinding mill → classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for barite and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~288 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 2.20 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 560 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 50% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 230 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 200–325 mesh weighting agent |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 560 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for barite, while a verifiable mass balance determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 230 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.