Gold ore underground mine: CAPEX justification — solution & design basis

The investment case compares purchase prices instead of lifetime cost — a 110 t/h design basis, configuration and acceptance checks.

Gold ore underground mine with CAPEX justification is normally resolved by checking the circuit against the saleable product specification first: normalise every quote to one written flow sheet. For a 110 t/h design point on gold ore, HAMAC would review jaw → cone / impact → screen, then confirm the settings with a written acceptance test. Start from the product specification and work backwards to the feed.

110 t/hindicative design point
60–200 MPacompressive strength
100–250 t/hscenario capacity band
350 kWorder-of-magnitude installed power
Key takeaways
  1. Gold ore is medium in abrasiveness and medium in moisture sensitivity; Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage.
  2. For underground mine the priority is compact footprint, constrained by restricted headroom, ventilation and haulage access.
  3. CAPEX justification typically appears as: the investment case compares purchase prices instead of lifetime cost.
  4. First corrective action: normalise every quote to one written flow sheet.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for gold ore underground mine

The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. Operator notes from the first month are often the best diagnostic data.

A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.

Gold ore — design basis (nominal values)
ParameterIndicative value / method
Raw materialGold ore · 60–200 MPa · abrasion medium
Design throughput110 t/h saleable product (100–250 t/h scenario band)
Maximum feed size~350 mm
Target product−10 mm mill feed or heap-leach agglomerate
Loose bulk density1.80 t/m³
Suggested circuitjaw → cone / impact → screen
Gold ore underground mine — Design basis for gold ore underground mine — HAMAC crushing and screening equipment
Gold ore underground mine — Design basis for gold ore underground mine — HAMAC crushing and screening equipment reference.

Why CAPEX justification appears in this circuit

The investment case compares purchase prices instead of lifetime cost. In a gold ore underground mine this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.

  • quotes assume different flow sheets and mass balances
  • freight, civils, erection and spares are excluded
  • availability is assumed at 100% in the payback model

A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. Confirm all figures in a written proposal before purchase.

Recommended equipment configuration

For gold ore at 110 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. Operator notes from the first month are often the best diagnostic data.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~138 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~18 mm at the secondary stage
Secondary / tertiarycone / impact
ScreeningMulti-deck screen sized for 30% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.80 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load

The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Gold ore underground mine — Recommended equipment configuration — HAMAC crushing and screening equipment
Gold ore underground mine — Recommended equipment configuration — HAMAC crushing and screening equipment reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 30% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.

  • Request a mass balance with each quotation
  • Confirm the Incoterm and named port
  • Sensitivity-test the payback at 75% utilisation
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 110 t/h nominal
GradingFull sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate
Crusher settingCSS measured and logged, ~18 mm starting point
PowerMain-drive current at steady feed, 350 kW connected load
WearLiner mass before and after, cost per saleable tonne

Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while compact footprint determines how much lost production actually costs. Start from the product specification and work backwards to the feed.

  • Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Operator notes from the first month are often the best diagnostic data. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Gold ore underground mine — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment
Gold ore underground mine — Cost, risk and what to confirm in writing — HAMAC crushing and screening equipment reference.
FAQ

Gold ore underground mine — questions answered

Direct answers to the questions buyers ask most often.

What causes CAPEX justification in a gold ore underground mine?

The investment case compares purchase prices instead of lifetime cost. The usual causes are quotes assume different flow sheets and mass balances; freight, civils, erection and spares are excluded; availability is assumed at 100% in the payback model. normalise every quote to one written flow sheet.

Which crusher train suits gold ore at 100–250 t/h?

A typical configuration is jaw → cone / impact → screen. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 110 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call