Design basis for calcite greenfield plant
The design basis starts with the rock, not the machine. Calcite is rated at 30–90 MPa compressive strength with very low abrasiveness, low moisture sensitivity and a loose bulk density around 1.35 t/m³. Whiteness and D97 control drive the circuit; contamination control and classifier stability are the priority. A change in one stage changes the circulating load in all the others.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 230 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of 200–2500 mesh GCC filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Calcite · 30–90 MPa · abrasion very low |
| Design throughput | 230 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | 200–2500 mesh GCC filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw → impact → Raymond / ball mill + classifier |

Why CAPEX justification appears in this circuit
The investment case compares purchase prices instead of lifetime cost. In a calcite greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- quotes assume different flow sheets and mass balances
- freight, civils, erection and spares are excluded
- availability is assumed at 100% in the payback model
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. HAMAC states nominal values alongside the conditions they were measured under.
Recommended equipment configuration
For calcite at 230 t/h the working train is jaw → impact → Raymond / ball mill + classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for calcite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~288 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 560 kW order-of-magnitude connected load |
The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 50% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Request a mass balance with each quotation
- Confirm the Incoterm and named port
- Sensitivity-test the payback at 75% utilisation
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 230 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 200–2500 mesh GCC filler |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 560 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
HAMAC states nominal values alongside the conditions they were measured under. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for calcite, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 230 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. HAMAC states nominal values alongside the conditions they were measured under. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
