Design basis for dolomite greenfield plant
The design basis starts with the rock, not the machine. Dolomite is rated at 60–180 MPa compressive strength with low–medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.42 t/m³. Suits impact crushing and downstream grinding; the fines fraction is often the most valuable product. Operator notes from the first month are often the best diagnostic data.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 210 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of aggregate, agricultural lime, filler powder.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Dolomite · 60–180 MPa · abrasion low–medium |
| Design throughput | 210 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | aggregate, agricultural lime, filler powder |
| Loose bulk density | 1.42 t/m³ |
| Suggested circuit | impact crusher → screen → optional Raymond mill |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a dolomite greenfield plant this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For dolomite at 210 t/h the working train is impact crusher → screen → optional Raymond mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for dolomite and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~263 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~18 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.42 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 510 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 30% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 210 t/h nominal |
| Grading | Full sieve analysis, agreed standard, aggregate, agricultural lime, filler powder |
| Crusher setting | CSS measured and logged, ~18 mm starting point |
| Power | Main-drive current at steady feed, 510 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for dolomite, while a verifiable mass balance determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 210 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
