● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Mobile plants

Copper ore underground mine: Long relocation and set-up time — solution & design basis

The plant loses more days to moving and erection than the contract allows — a 110 t/h design basis, configuration and acceptance checks.

Copper ore underground mine with long relocation and set-up time is normally resolved by checking the circuit against the saleable product specification first: standardise plug-in connections and conveyor interfaces. For a 110 t/h design point on copper ore, HAMAC would review jaw → cone → screen → grinding circuit, then confirm the settings with a written acceptance test. On site, feed variability hides problems that a test sample never shows.

110 t/hindicative design point
80–220 MPacompressive strength
100–250 t/hscenario capacity band
270 kWorder-of-magnitude installed power
Key takeaways
  1. Copper ore is medium in abrasiveness and medium in moisture sensitivity; Product top size is set by the downstream mill, so a closed crushing circuit with tight screen control protects grinding energy.
  2. For underground mine the priority is compact footprint, constrained by restricted headroom, ventilation and haulage access.
  3. Long relocation and set-up time typically appears as: the plant loses more days to moving and erection than the contract allows.
  4. First corrective action: standardise plug-in connections and conveyor interfaces.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for copper ore underground mine

The design basis starts with the rock, not the machine. Copper ore is rated at 80–220 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.90 t/m³. Product top size is set by the downstream mill, so a closed crushing circuit with tight screen control protects grinding energy. Measurements are only comparable when the sieve standard is the same.

A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of −12 mm mill feed.

Copper ore — design basis (nominal values)
ParameterIndicative value / method
Raw materialCopper ore · 80–220 MPa · abrasion medium
Design throughput110 t/h saleable product (100–250 t/h scenario band)
Maximum feed size~450 mm
Target product−12 mm mill feed
Loose bulk density1.90 t/m³
Suggested circuitjaw → cone → screen → grinding circuit
Copper ore underground mine — Design basis for copper ore underground mine — HAMAC mobile crushing plant
Copper ore underground mine — Design basis for copper ore underground mine — HAMAC mobile crushing plant reference.

Why long relocation and set-up time appears in this circuit

The plant loses more days to moving and erection than the contract allows. In a copper ore underground mine this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.

  • electrical and conveyor connections differ between modules
  • transport permits and axle loads were checked too late
  • no written set-up sequence exists for the crew

Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Confirm all figures in a written proposal before purchase.

Recommended equipment configuration

For copper ore at 110 t/h the working train is jaw → cone → screen → grinding circuit. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for copper ore and for a softer rock. Measurements are only comparable when the sieve standard is the same.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~138 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~18 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 30% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.90 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 270 kW order-of-magnitude connected load

The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Copper ore underground mine — Recommended equipment configuration — HAMAC mobile crushing plant
Copper ore underground mine — Recommended equipment configuration — HAMAC mobile crushing plant reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 18 mm, a circulating load around 30% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.

  • Time a full move from stop to first feed
  • Count lifting operations and crane hours
  • Record every connection that needs a tool on site
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 110 t/h nominal
GradingFull sieve analysis, agreed standard, −12 mm mill feed
Crusher settingCSS measured and logged, ~18 mm starting point
PowerMain-drive current at steady feed, 270 kW connected load
WearLiner mass before and after, cost per saleable tonne

Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for copper ore, while compact footprint determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.

  • Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Copper ore underground mine — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant
Copper ore underground mine — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant reference.
FAQ

Copper ore underground mine — questions answered

Direct answers to the questions buyers ask most often.

What causes long relocation and set-up time in a copper ore underground mine?

The plant loses more days to moving and erection than the contract allows. The usual causes are electrical and conveyor connections differ between modules; transport permits and axle loads were checked too late; no written set-up sequence exists for the crew. standardise plug-in connections and conveyor interfaces.

Which crusher train suits copper ore at 100–250 t/h?

A typical configuration is jaw → cone → screen → grinding circuit. Product top size is set by the downstream mill, so a closed crushing circuit with tight screen control protects grinding energy. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 110 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call