Design basis for gabbro asphalt aggregate supply
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. Record the setting before adjusting it, or the baseline is lost.
A asphalt aggregate supply must produce cubical, low-fines chips for asphalt plants, constrained by a narrow 5–16 mm fraction with low moisture. The commercial priority is particle shape. For this combination HAMAC works from an indicative design point of 130 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 130 t/h saleable product (100–220 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why restricted site footprint appears in this circuit
The required circuit will not fit the available bench or yard. In a gabbro asphalt aggregate supply this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- conveyor inclines and transfer towers consume most of the area
- stockpile and maintenance access were not included in the layout
- the flow sheet assumes a straight-line arrangement
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) draw the layout to scale with conveyor inclines; 2) check crusher removal clearance; 3) verify truck turning radius and stockpile reach. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For gabbro at 130 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~163 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 350 kW order-of-magnitude connected load |
The corrective actions for restricted site footprint are applied on top of this base circuit: fold the circuit with a compact elevator or modular tower; place the screen above the crusher in a closed loop; reserve a maintenance lane for liner change-outs.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 50% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Draw the layout to scale with conveyor inclines
- Check crusher removal clearance
- Verify truck turning radius and stockpile reach
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 130 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 350 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while particle shape determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 130 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.