Design basis for gabbro greenfield plant
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. Indicative values are starting points for a design, not guarantees.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 220 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 220 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a gabbro greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For gabbro at 220 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~275 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 590 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 40% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 220 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 590 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 220 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.