Design basis for construction & demolition waste greenfield plant
The design basis starts with the rock, not the machine. Construction & demolition waste is rated at variable compressive strength with variable abrasiveness, variable moisture sensitivity and a loose bulk density around 1.20 t/m³. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. A change in one stage changes the circulating load in all the others.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 220 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of 0–4, 4–20, 20–40 mm recycled aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Construction & demolition waste · variable · abrasion variable |
| Design throughput | 220 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | 0–4, 4–20, 20–40 mm recycled aggregate |
| Loose bulk density | 1.20 t/m³ |
| Suggested circuit | mobile impact + magnet + picking → screen |

Why frequent site relocation appears in this circuit
A stationary plant cannot follow the working face economically. In a construction & demolition waste greenfield plant this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- haul distance grows as the face advances
- civil foundations make relocation a major project
- the contract duration is shorter than the plant payback period
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) verify transport width and axle loads for local roads; 3) confirm set-up can be done with the site crane available. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For construction & demolition waste at 220 t/h the working train is mobile impact + magnet + picking → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for construction & demolition waste and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~275 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.20 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 650 kW order-of-magnitude connected load |
The corrective actions for frequent site relocation are applied on top of this base circuit: use wheel or tracked units with on-board screens; design modular skids that fit standard container dimensions; standardise electrical plug-in connections between modules.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 40% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Time a full move from stop to first feed
- Verify transport width and axle loads for local roads
- Confirm set-up can be done with the site crane available
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 220 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–4, 4–20, 20–40 mm recycled aggregate |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 650 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for construction & demolition waste, while a verifiable mass balance determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 220 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.