Design basis for copper ore remote site
The design basis starts with the rock, not the machine. Copper ore is rated at 80–220 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.90 t/m³. Product top size is set by the downstream mill, so a closed crushing circuit with tight screen control protects grinding energy. A change in one stage changes the circulating load in all the others.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 70 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of −12 mm mill feed.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Copper ore · 80–220 MPa · abrasion medium |
| Design throughput | 70 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | −12 mm mill feed |
| Loose bulk density | 1.90 t/m³ |
| Suggested circuit | jaw → cone → screen → grinding circuit |

Why restricted site footprint appears in this circuit
The required circuit will not fit the available bench or yard. In a copper ore remote site this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- conveyor inclines and transfer towers consume most of the area
- stockpile and maintenance access were not included in the layout
- the flow sheet assumes a straight-line arrangement
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) draw the layout to scale with conveyor inclines; 2) check crusher removal clearance; 3) verify truck turning radius and stockpile reach. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For copper ore at 70 t/h the working train is jaw → cone → screen → grinding circuit. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for copper ore and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~88 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.90 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 170 kW order-of-magnitude connected load |
The corrective actions for restricted site footprint are applied on top of this base circuit: fold the circuit with a compact elevator or modular tower; place the screen above the crusher in a closed loop; reserve a maintenance lane for liner change-outs.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 30% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Draw the layout to scale with conveyor inclines
- Check crusher removal clearance
- Verify truck turning radius and stockpile reach
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 70 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −12 mm mill feed |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 170 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for copper ore, while energy and spares autonomy determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 70 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.