Design basis for gabbro remote site
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. A change in one stage changes the circulating load in all the others.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 80 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 80 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why capacity shortfall appears in this circuit
The line stabilises at 70–85% of its quoted throughput. In a gabbro remote site this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.
- the mass balance was sized for fresh feed without circulating load
- a feeder or conveyor reaches its volumetric limit before the crusher does
- screen efficiency falls as near-size material builds up in the return loop
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) weigh the return belt over a full shift; 2) log crusher power draw against feeder rate; 3) sieve the screen oversize for near-size content. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For gabbro at 80 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~100 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 240 kW order-of-magnitude connected load |
The corrective actions for capacity shortfall are applied on top of this base circuit: recalculate the full mass balance including the return stream; add surge capacity ahead of the secondary stage to hold choke feed; resize the limiting conveyor or screen deck rather than the crusher.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 40% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Weigh the return belt over a full shift
- Log crusher power draw against feeder rate
- Sieve the screen oversize for near-size content
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 80 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 240 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while energy and spares autonomy determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 80 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.