Design basis for construction & demolition waste contract crushing
The design basis starts with the rock, not the machine. Construction & demolition waste is rated at variable compressive strength with variable abrasiveness, variable moisture sensitivity and a loose bulk density around 1.20 t/m³. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. Operator notes from the first month are often the best diagnostic data.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 500 mm and target fractions of 0–4, 4–20, 20–40 mm recycled aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Construction & demolition waste · variable · abrasion variable |
| Design throughput | 120 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~500 mm |
| Target product | 0–4, 4–20, 20–40 mm recycled aggregate |
| Loose bulk density | 1.20 t/m³ |
| Suggested circuit | mobile impact + magnet + picking → screen |

Why long relocation and set-up time appears in this circuit
The plant loses more days to moving and erection than the contract allows. In a construction & demolition waste contract crushing this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- electrical and conveyor connections differ between modules
- transport permits and axle loads were checked too late
- no written set-up sequence exists for the crew
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For construction & demolition waste at 120 t/h the working train is mobile impact + magnet + picking → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for construction & demolition waste and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~150 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.20 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 260 kW order-of-magnitude connected load |
The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 60% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Time a full move from stop to first feed
- Count lifting operations and crane hours
- Record every connection that needs a tool on site
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 120 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–4, 4–20, 20–40 mm recycled aggregate |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 260 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for construction & demolition waste, while mobility and fast set-up determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.