● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Mobile plants

Construction & demolition waste contract crushing: Long relocation and set-up time — solution & design basis

The plant loses more days to moving and erection than the contract allows — a 120 t/h design basis, configuration and acceptance checks.

Construction & demolition waste contract crushing with long relocation and set-up time is normally resolved by checking the circuit against the saleable product specification first: standardise plug-in connections and conveyor interfaces. For a 120 t/h design point on construction & demolition waste, HAMAC would review mobile impact + magnet + picking → screen, then confirm the settings with a written acceptance test. A supplier can only guarantee a figure when the test conditions are written down.

120 t/hindicative design point
variablecompressive strength
80–200 t/hscenario capacity band
260 kWorder-of-magnitude installed power
Key takeaways
  1. Construction & demolition waste is variable in abrasiveness and variable in moisture sensitivity; Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone.
  2. For contract crushing the priority is mobility and fast set-up, constrained by short project duration and no permanent foundations.
  3. Long relocation and set-up time typically appears as: the plant loses more days to moving and erection than the contract allows.
  4. First corrective action: standardise plug-in connections and conveyor interfaces.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for construction & demolition waste contract crushing

The design basis starts with the rock, not the machine. Construction & demolition waste is rated at variable compressive strength with variable abrasiveness, variable moisture sensitivity and a loose bulk density around 1.20 t/m³. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. Operator notes from the first month are often the best diagnostic data.

A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 120 t/h of saleable product, with a maximum feed top size near 500 mm and target fractions of 0–4, 4–20, 20–40 mm recycled aggregate.

Construction & demolition waste — design basis (nominal values)
ParameterIndicative value / method
Raw materialConstruction & demolition waste · variable · abrasion variable
Design throughput120 t/h saleable product (80–200 t/h scenario band)
Maximum feed size~500 mm
Target product0–4, 4–20, 20–40 mm recycled aggregate
Loose bulk density1.20 t/m³
Suggested circuitmobile impact + magnet + picking → screen
Construction & demolition waste contract crushing — Design basis for construction & demolition waste contract crushing — HAMAC mobile crushing plant
Construction & demolition waste contract crushing — Design basis for construction & demolition waste contract crushing — HAMAC mobile crushing plant reference.

Why long relocation and set-up time appears in this circuit

The plant loses more days to moving and erection than the contract allows. In a construction & demolition waste contract crushing this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.

  • electrical and conveyor connections differ between modules
  • transport permits and axle loads were checked too late
  • no written set-up sequence exists for the crew

Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Confirm all figures in a written proposal before purchase.

Recommended equipment configuration

For construction & demolition waste at 120 t/h the working train is mobile impact + magnet + picking → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for construction & demolition waste and for a softer rock. Operator notes from the first month are often the best diagnostic data.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~150 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~30 mm at the secondary stage
Secondary / tertiaryscreen
ScreeningMulti-deck screen sized for 60% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.20 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 260 kW order-of-magnitude connected load

The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Construction & demolition waste contract crushing — Recommended equipment configuration — HAMAC mobile crushing plant
Construction & demolition waste contract crushing — Recommended equipment configuration — HAMAC mobile crushing plant reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 60% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.

  • Time a full move from stop to first feed
  • Count lifting operations and crane hours
  • Record every connection that needs a tool on site
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 120 t/h nominal
GradingFull sieve analysis, agreed standard, 0–4, 4–20, 20–40 mm recycled aggregate
Crusher settingCSS measured and logged, ~30 mm starting point
PowerMain-drive current at steady feed, 260 kW connected load
WearLiner mass before and after, cost per saleable tonne

Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for construction & demolition waste, while mobility and fast set-up determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.

  • Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 120 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Operator notes from the first month are often the best diagnostic data. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Construction & demolition waste contract crushing — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant
Construction & demolition waste contract crushing — Cost, risk and what to confirm in writing — HAMAC mobile crushing plant reference.
FAQ

Construction & demolition waste contract crushing — questions answered

Direct answers to the questions buyers ask most often.

What causes long relocation and set-up time in a construction & demolition waste contract crushing?

The plant loses more days to moving and erection than the contract allows. The usual causes are electrical and conveyor connections differ between modules; transport permits and axle loads were checked too late; no written set-up sequence exists for the crew. standardise plug-in connections and conveyor interfaces.

Which crusher train suits construction & demolition waste at 80–200 t/h?

A typical configuration is mobile impact + magnet + picking → screen. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 120 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call