Design basis for gold ore remote site
The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. A change in one stage changes the circulating load in all the others.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 90 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gold ore · 60–200 MPa · abrasion medium |
| Design throughput | 90 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | −10 mm mill feed or heap-leach agglomerate |
| Loose bulk density | 1.80 t/m³ |
| Suggested circuit | jaw → cone / impact → screen |

Why long relocation and set-up time appears in this circuit
The plant loses more days to moving and erection than the contract allows. In a gold ore remote site this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- electrical and conveyor connections differ between modules
- transport permits and axle loads were checked too late
- no written set-up sequence exists for the crew
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For gold ore at 90 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~113 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone / impact |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.80 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 290 kW order-of-magnitude connected load |
The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 50% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Time a full move from stop to first feed
- Count lifting operations and crane hours
- Record every connection that needs a tool on site
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 90 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 290 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while energy and spares autonomy determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 90 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.