Design basis for basalt contract crushing
The design basis starts with the rock, not the machine. Basalt is rated at 150–300 MPa compressive strength with high abrasiveness, low moisture sensitivity and a loose bulk density around 1.50 t/m³. Very abrasive and tough; wear cost per tonne, not peak throughput, usually decides the circuit and the liner alloy. Operator notes from the first month are often the best diagnostic data.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 80 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of railway ballast, 0–5, 5–16, 16–31.5 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Basalt · 150–300 MPa · abrasion high |
| Design throughput | 80 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | railway ballast, 0–5, 5–16, 16–31.5 mm |
| Loose bulk density | 1.50 t/m³ |
| Suggested circuit | jaw → cone → VSI → 3-deck screen |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a basalt contract crushing this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For basalt at 80 t/h the working train is jaw → cone → VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for basalt and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~100 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.50 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 260 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 20% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 80 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast, 0–5, 5–16, 16–31.5 mm |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 260 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for basalt, while mobility and fast set-up determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 80 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.