● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Commissioning

Bauxite high-altitude site: Tramp metal damage — solution & design basis

A bucket tooth or rebar reaches the chamber and damages liners — a 100 t/h design basis, configuration and acceptance checks.

Bauxite high-altitude site with tramp metal damage is normally resolved by checking the circuit against the saleable product specification first: fit a magnetic separator and a belt metal detector. For a 100 t/h design point on bauxite, HAMAC would review impact crusher → washing screen, then confirm the settings with a written acceptance test. Most of these problems are diagnosed at the screen, not at the crusher.

100 t/hindicative design point
30–90 MPacompressive strength
100–250 t/hscenario capacity band
220 kWorder-of-magnitude installed power
Key takeaways
  1. Bauxite is low in abrasiveness and high in moisture sensitivity; Sticky, clay-rich feed blocks grizzlies and screens; wet processing and generous transfer chutes are usual.
  2. For high-altitude site the priority is drive and cooling margins, constrained by reduced air density and large day/night temperature swings.
  3. Tramp metal damage typically appears as: a bucket tooth or rebar reaches the chamber and damages liners.
  4. First corrective action: fit a magnetic separator and a belt metal detector.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for bauxite high-altitude site

The design basis starts with the rock, not the machine. Bauxite is rated at 30–90 MPa compressive strength with low abrasiveness, high moisture sensitivity and a loose bulk density around 1.35 t/m³. Sticky, clay-rich feed blocks grizzlies and screens; wet processing and generous transfer chutes are usual. Indicative values are starting points for a design, not guarantees.

A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of sized ore and washed fines.

Bauxite — design basis (nominal values)
ParameterIndicative value / method
Raw materialBauxite · 30–90 MPa · abrasion low
Design throughput100 t/h saleable product (100–250 t/h scenario band)
Maximum feed size~400 mm
Target productsized ore and washed fines
Loose bulk density1.35 t/m³
Suggested circuitimpact crusher → washing screen
Bauxite high-altitude site — Design basis for bauxite high-altitude site — HAMAC impact crusher
Bauxite high-altitude site — Design basis for bauxite high-altitude site — HAMAC impact crusher reference.

Why tramp metal damage appears in this circuit

A bucket tooth or rebar reaches the chamber and damages liners. In a bauxite high-altitude site this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.

  • no magnet or detector ahead of the crusher
  • hydraulic relief and tramp-release settings are untested
  • demolition feed is not pre-sorted

Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Agree the acceptance test and sampling method before the order is placed.

Recommended equipment configuration

For bauxite at 100 t/h the working train is impact crusher → washing screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for bauxite and for a softer rock. Indicative values are starting points for a design, not guarantees.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~125 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~30 mm at the secondary stage
Secondary / tertiarywashing screen
ScreeningMulti-deck screen sized for 20% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.35 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 220 kW order-of-magnitude connected load

The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Bauxite high-altitude site — Recommended equipment configuration — HAMAC impact crusher
Bauxite high-altitude site — Recommended equipment configuration — HAMAC impact crusher reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 20% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.

  • Test the detector with a sample metal piece each week
  • Inspect the chamber after any release event
  • Log every tramp incident and its cause
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 100 t/h nominal
GradingFull sieve analysis, agreed standard, sized ore and washed fines
Crusher settingCSS measured and logged, ~30 mm starting point
PowerMain-drive current at steady feed, 220 kW connected load
WearLiner mass before and after, cost per saleable tonne

Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for bauxite, while drive and cooling margins determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.

  • Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Indicative values are starting points for a design, not guarantees. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Bauxite high-altitude site — Cost, risk and what to confirm in writing — HAMAC impact crusher
Bauxite high-altitude site — Cost, risk and what to confirm in writing — HAMAC impact crusher reference.
FAQ

Bauxite high-altitude site — questions answered

Direct answers to the questions buyers ask most often.

What causes tramp metal damage in a bauxite high-altitude site?

A bucket tooth or rebar reaches the chamber and damages liners. The usual causes are no magnet or detector ahead of the crusher; hydraulic relief and tramp-release settings are untested; demolition feed is not pre-sorted. fit a magnetic separator and a belt metal detector.

Which crusher train suits bauxite at 100–250 t/h?

A typical configuration is impact crusher → washing screen. Sticky, clay-rich feed blocks grizzlies and screens; wet processing and generous transfer chutes are usual. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 100 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call